Following its topping off ceremony on 07 June 2013, the overall construction works of Admiral Baysuites is now at 89% while the overall accomplishment status is at 69%.

 

In summary: waterproofing works is at 60%; the installation of balcony railings is at 47%; plumbing and sanitary works is at 88%; electrical works is at 69%; FDAS works is at 42%; auxiliary works is at 42%; mechanical works is at 62%; fire protection works is at 72%; the installation of glass, doors and windows in the East Wing is at 88% while it is at 47% in the West Wing; interior painting is at 35%; and the exterior painting is at 38%.

 

Admiral Baysuites is scheduled to be completed in 2014. For more information, like our official Facebook page at www.facebook.com/admiralbaysuites