Construction Updates

September 2015

Turnover are ongoing for the substantially completed Admiral Baysuites Project. Construction remains on schedule with an overall accomplishment percentage of 97.81%.

 

For the period July – September 2015, residential units, the English Garden and the West Amenity areas were substantially completed while the East Amenity areas were fully accomplished. Punchlisting is ongoing and MEPF Systems are all operational.