June 2015

Construction for Admiral Baysuites is almost complete at 94.82%.

 

There is a simultaneous finishing works carried out on entire building up to 52nd  floor. , quality check is on-going 29th to 45th floor. To date, all units up until the 28th floor are all ready for turnover.

 

Apace with these significant developments, the lobby, 8th and 29th floors and the English Garden at the top floor are subject for finishing touches.

 

Turnover is currently ongoing.

 